WLWP Timetable

The West London Waste Plan (cunning, or otherwise) is behind schedule, but key milestones for the contractors are:

March 2011 
  • Publication of the WLWP document and sustainability proposal
April-May 2011
  • Pre-qualification of bidders
May-June 2011
  • WLWP examination in public
December 2011
  • WLWP adopted
January 2012
  • Short-listing of bidders
June 2012
  • Possible further short-listing of bidders
September 2012
  • Final tenders
October 2012
  • Preferred bidder/tender award.
  • 2012-14: Planning
  • 2014-16: Construction of new plants
  • 2015-16: Plants operational.